Bromley Heath Viaduct Kept On Track
Bromley Heath Viaduct Project
Drillcut (UK) Limited have completed there project ahead of programme keeping Bristol’s roads on track ahead of project completion
Drillcut (UK) Limited Safely and quickly removed 48 No. Lumps of concrete ranging from 8 tonnes to 2.5 tonnes of reinforced concrete sections removed in 14 Days
Diamond track sawing and wire sawing was used throughout to cut reinforced concrete bridge into sections to aid in removal of south cantilever for re strengthening the 1960’s structure and provide improvements for cyclists and pedestrians.